Roswell's Park Upgrades Landed Inland This Fall, While the River Park Waits for 2027

Turtles are back at the Roswell Area Park pond. The city says turtles and frogs started returning while construction was still wrapping up, and the pond trail officially reopened with a ribbon-cutting on Thursday, Sept. 10. Down on the Chattahoochee, Riverside Park has been closed since dusk on Sunday, Feb. 1. It's projected to reopen in Summer 2027, and its sprayground is closed for the duration.

Both projects are paid for by the same voter-approved 2022 Parks Bond. Between July and early October, the city finished four bond-funded projects, and all of them are away from the Chattahoochee. Meanwhile, the biggest river project broke ground in March and isn't projected to finish until next summer. So for this fall, and for every season until Riverside reopens, Roswell's new park time is inland. You reach the river through the smaller parks on either side of Riverside Road.

What finished, and what each one is still waiting on

None of this year's ribbon-cuttings handed back a project with nothing left to do. Each has one more piece coming:

Project

Reopened

Cost

What's still ahead

Roswell Area Park pond

Ribbon-cutting Sept. 10, 2026

About $3.1 million

Fishing is restricted until the restocked pond settles, expected late summer or fall 2027

Grimes Bridge Park soccer fields

Ribbon-cutting Sept. 24, 2026

$4.1 million

29 new trees to be planted this fall, no date set

Hardscrabble Road Multi-Use Trail

Announced open July 9, 2026

About $2.5 million

Nothing announced

Riverside Park

Closed Feb. 1, 2026

$13.8 million total budget

Projected to reopen Summer 2027

The fourth finished project is citywide. Roswell installed 699 LED fixtures on 167 existing poles at city athletic fields and racquet courts, and marked it with a virtual ribbon-cutting instead of a ceremony on site. You'll see it on the next weeknight game or evening tennis match, as the days get shorter through November.

The pond at Roswell Area Park is a walk for now, not a fishing trip

The pond work took nearly a year. Crews dredged the pond, rebuilt the embankment, upgraded stormwater pipes, added new forebays, and fixed the retaining walls and the trail that circles the water. They also planted 35 new trees, plus native and aquatic plants along the edge, and placed logs in the water so turtles have somewhere to bask.

That's why a loop on the improved trail this October is more about wildlife than fishing. According to Roswell Connections, the city's news site, about 15,000 fish will be added in phases as the pond stabilizes, and fishing stays temporarily restricted until then. The current estimate for fishing to resume is late summer or fall 2027. If a kid in your house has been asking to bring a rod, leave it home this season and bring a turtle-spotting challenge instead.

Grimes Bridge Park gets more game time, and a little more shade is coming

At Grimes Bridge Park, Soccer Fields #1 and #2 went from natural grass to artificial turf. That means the fields can be set up in different configurations and can be booked more often. The $4.1 million project also included a rebuilt retaining wall, a new plaza and stairway connection, new fencing and netting, and a restored detention pond.

Turf doesn't turn to mud, which matters in a fall where rain can wipe out a Saturday of games. Steven Malone, director of Roswell Recreation, Parks, Historic & Cultural Affairs, put it this way at the ceremony, as reported by Roswell Connections:

"Today, these fields have a new playing surface, a rebuilt foundation and a better experience for players and spectators."

The same article says city athletics staff will schedule the fields throughout the week, and that a landscape plan will add 29 trees to the park this fall. If you're on the sidelines in late October or November, you may get to watch the planting crews too.

Hardscrabble Road is the new way to get around without a car

The Hardscrabble Road Multi-Use Trail is the least showy of the four projects, and it's the one you can use on a regular Tuesday. It adds about 3,000 feet of 8- to 10-foot-wide trail on the north side of Hardscrabble Road between King Road and Whittingham Place, plus about 1,200 feet of 8-foot-wide trail along King Road. Both pieces connect to the trails already on those roads.

The city's announcement lists pedestrians, cyclists, students and golf cart users as the people it's built for. If you live near that stretch, a fall evening walk or a golf cart trip toward Roswell High School now has its own lane, separate from car traffic.

Riverside Park is out for the season, and its regulars need a plan B

All that inland progress stands out because of the park that's missing. Riverside Park covers about 21 acres on the Chattahoochee and gets more than 130,000 visitors a year. Since it opened in 2002, it has hosted the Riverside Sounds Concert Series. City Council approved a $12.3 million construction contract with MAPP on Dec. 8, 2025, as part of a $13.8 million total budget. The groundbreaking was on Friday, March 13, 2026.

The city says the park is expected to reopen in Summer 2027, and that's a forecast, not a fixed date. Riverside Sounds is on hold until further notice.

The city's Riverside Park page says pedestrian routes around the site will stay open. It also sends overflow parking to Ace Sand Park at 705 Riverside Road and Don White Memorial Park at 925(B) Riverside Road. Azalea Park and River Landing are specifically not alternate parking.

Where to reach the Chattahoochee this fall

Here are the riverfront spots near Riverside Park, with the amenities the city and the National Park Service list for each:

  1. Don White Memorial Park, 925 Riverside Road. The city lists a canoe and kayak launch, fishing docks, hiking and multi-use trails, outdoor fitness equipment, picnic areas, restrooms and volleyball. It's also one of the two designated parking spots for the Riverside closure, so it's the easiest swap if your usual plan was a walk along the river.
  2. Azalea Park, 203 Azalea Drive. The city lists a canoe and kayak launch, river access, walking trails, fishing, a picnic area, a playground and restrooms. With the Riverside sprayground closed, this is the riverfront playground on the list.
  3. Roswell River Landing, 245 Azalea Drive. It's mainly an event venue, but the city's page lists an observation deck and a canoe and kayak launch.
  4. Vickery Creek and Island Ford, Chattahoochee River National Recreation Area. The National Park Service map lists 7.4 miles of hiking trail and a canoe launch at Vickery Creek, and 4.9 miles of trail and a canoe launch at Island Ford. If Riverside was a stroll for you and you want something longer for fall, these are your trail options.

Riverside Road itself is the next project on the list

The river corridor has a second project coming. On July 13, 2026, Roswell Mayor and Council approved the construction contract for the Riverside Road Corridor Improvement Project. It covers about two miles of Riverside Road between Riviera Road and Old Alabama Road.

The plan includes:

  • A modern roundabout at River Lake Drive
  • A new traffic signal at Taimen Drive
  • Raised medians, dedicated bike lanes and new sidewalks
  • Improved pedestrian crossings, drainage work and landscaping

According to Roswell Connections, there are 95 specimen trees in the corridor. The project removes 23 of them and keeps 72, about 76 percent. In all, 129 trees come out and 49 new ones go in. Work begins after the contractor mobilizes. Once it starts, the city expects periodic lane closures, temporary traffic shifts and active work zones, and says access to neighborhoods, businesses, schools and parks will be kept open whenever possible. Since the road leads to Don White and Ace Sand, the city's Riverside Road updates are worth checking before you head to the river.

A home near the Roswell Area Park pond, the new Hardscrabble trail or one of the river parks has its own story to tell buyers, and that story should show up in the photos and the video. If you're curious what your place could sell for and how to stage it around what's close by, Jodi Godfrey would love to help. Schedule your free home valuation & staging consult.

main

happy to help

Work with

Why the House Chick? When considering my logo, I wanted to keep it simple, memorable, and friendly. I also wanted it to reflect a piece of me therefore; I added my first name to make it personal. A brand was born: Jodi The House Chick

Follow Me on Instagram